The process of the AAC productions line
Total posts 109
Joined 8 year(s) ago
Posted 02:11 AM Friday, August 21, 2015   [ quote ]

1.First the loader loads sand material into “material hopper”, the sand through belt conveyer enter into “ball mill machine” (2) to crush into powder slurry. In the crushing process ,water will be added.into ball mill machine in the same time . so finally ball mill machine will produce sand slurry
diesel concrete mixer,mini mix concrete batching plant for sale,mobile brick making machine,

2. Sand slurry out of ball mill machine enters into concrete pit , slurry will be sent into two “slurry store mixer“”(3) through “slurry pump”

3.When we need slurry to batch ,the slurry be released from “slurry store mixer” and enter into slurry pit which under the “slurry store mixer” . There have another sand slurry will enter into “ slurry measure scale” through “slurry pump”. In the same time, the lime mini mix concrete batching plant, cement , gypsum, will be added into lime cement gypsum scale automatically one by one.

After measuring sand, lime, cement, gypsum ,they will be added into “slurry pouring mixer “ automatically ,In the same time ,the aluminum will be add into “slurry pouring mixer “by manual after manual scale measure .When all material mixing in the “slurry store mixer”, after 4-6 minutes mixing , all material will be pour into “Mould box”.Except that aluminum powder will be added by manual, the whole batching process is operated by PLC in control room.

4 After slurry be pour into mould box ,”frequency conversion pouring ferry car” will take the mould into curing room area automatically , all the mould box will be add into curing room to cure automatically through PLC in control room

5 when mould box moving in the curing room mobile mini concrete batching plant,all mould boxing moving process is automatically ,under mould box there will be roller that will support mould moving.

6.After 1.5-2 hours pre-curing in curing area , the mould box with foam block will move into “reversal crane” position , reversal crane will lift and do the de-mould work, put the block with pallet on “cutting translational cart” electric cement mixer for sale, then there are level cutting and vertical cutting process, the cutting process will be controlled in the control room automatically .

7. After cutting the block ,It will be transported into steam trolley trough “ transport block crane” , the crane will be controlled by wireless control device ,also there have the wire control device for spare alternating.

8 6 steam trolleys {12 blocks} will be sent to autoclave through windless machine

9.First we need 1.5 hours to discharge cool air in autolcaves and one hour to add pressure. then use

0.5 hour to reach 1.0-1.3 Mpa quickly. In 1.0-1.3 Map period ,we need keep about steam 5-6 hours. after that we will need 1.5-2 hours to release the pressure and steam . After about 10-11 hours ,the blocks could be taken out and transported in store area.

10 The empty pallet with trolley will be sent back to reversal crane and organize new moulds to reuse . trolley will be transported for entering into autoclave area to re use.